This page contains pictures of the Jackson Covered Bridge from February 2007
to April 2007. Use the quick links to see pictures from a specific
month.
February 2007 |
|
|
February 3rd |
|
|
|
February 3rd The temporary bridge is complete and
the dollies have been placed under the bridge. The dollies have built in jacks
which will be used to lift the bridge. The bridge was to be moved on Tuesday,
February 6th, however, the temperature is below 10 degrees. The move has now been
postponed until next week when the temperature should be warmer. These pictures were
taken from the south side of the bridge.
|
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
Back to Top |
February 20th |
|
|
|
February 20th The Jackson Bridge is finally ready to
be moved. The weather has agreed to cooperate and the bridge will be moved on
February 21st.
|
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
Back to Top |
February 21st |
|
|
|
February 21st The Jackson Bridge was moved off
of the abutments and placed on the road bed. The bridge move took approximately
3 hours to be moved. The bridge was pulled using a winch attached to a truck.
|
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
Back to Top |
|
|
March 2007 |
|
|
March 11th |
|
|
|
March 11th The Jackson Bridge has been braced and
the reconstruction has started. Some more boards have been removed from the
bridge.
|
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
March 11th Over the years the Jackson Bridge had
been damaged and repairs were made. Here are two pictures of steel beams that
were added to the bridge to reinforce damaged timbers.
|
|
|
|
 |
|
|
|
 |
|
|
|
March 11th The cribbing (temporary bridge) built to
move the Jackson bridge was left in place, so the bridge can be moved back onto
the abutments. However, rain and melting snow caused Sugar Creek to flood. The
flood waters of Sugar Creek have already destroyed part of the cribbing. Logs
floating down the creek are now resting on some of the cribbing supports.
|
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
Back to Top |
|
|
March 20th |
|
|
|
March 20th Scaffolding has been erected to
support the Jackson Bridge as the original timbers are being removed.
The floor has been removed and the arches are being disassembled.
|
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
March 20th Some of the metal supports that
were placed on the bridge in earlier repairs have been removed.
|
|
|
|
 |
|
|
|
March 20th The following pictures were
taken from the south side of the creek and show the current state of
the temporary bridge (cribbing).
|
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
Back to Top |
April 2007 |
|
|
April 5th |
|
|
|
April 5th The work on the Jackson Bridge is
making good progess. The contractors have removed the bowing of the
bridge. (The bridge was twisted and one of the engineers speculated
that it had been hit by a tornado.) The lower cords of the west side
of the bridge are currently being replaced. The workers have also
removed most of the cribbing from the creek, the cribbing was creating
a dam and causing bank erosion.
|
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
April 5th New treated laminated timbers are
being installed on the bridge. Piles of the new timbers have been delivered
for the bridge.
|
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
April 15th |
|
April 15th The workers continue to make
progress on the Jackson Bridge. The siding supports are being removed
so the arches can be repaired. The workers have also removed all of the
cribbing from Sugar Creek.
|
|
|
|
 |
|
|
|
|
|
 |
|
|
|
 |
|
|
|
April 15th Here is a picture of Sugar Creek
with the cribbing removed.
|
|
|
|
 |
|
|
|
April 15th The arches on the east side of the
bridge are also being repaired.
|
|
|
|
 |
|
|
|
 |
|
|
|
April 15th Here are some of the rotten timbers
that have been removed from the Jackson bridge.
|
|
|
|
 |
|
|
|
 |
|
|
Back to Top |
April 28th |
|
April 28th The lower cords on the east side
of the bridge are being replaced. The north end of the bridge is also being
reconstructed. These pictures show the west side of the bridge and the
north end.
|
|
|
|
 |
|
|
|
 |
|
|
|
 |
|
|
|
April 28th These pictures were taken from the
east side of the bridge.
|
|
|
|
 |
|
|
|
 |
|
|
Back to Top |