The Jackson Covered Bridge over Sugar Creek is being rehabilitated. Work
on the $1.4 million Federal Aid project has started. The project will
include the removal of the roof and siding. The bridge frame will then be
moved off of the abutments for rehabilitation as well. The bridge is
scheduled to be removed from the abutments in early 2007. The purpose
of this website is to track the progress of the bridge rehabilitation.
Quick Links to Photos
June 2006 Photos
December 2006 Photos
January 2007 Photos
February 2007 Photos
March 2007 Photos
April 2007 Photos
May 2007 Photos
June 2007 Photos
July 2007 Photos
August 2007 Photos
September 2007 Photos
October 2007 Photos
May 2007 |
|
|
May 10th |
|
|
|
May 10th The workers continue to make
progress on the bridge. The damaged wood of the arches have been
removed and new lower cords are being installed.
|
|
|
|
|
|
|
|
|
|
|
|
May 10th Work is being done on the upright
posts.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
May 10th Here are some of the old joint
pieces that were removed from the bridge.
|
|
|
|
|
|
|
Back to Top |
May 25th |
|
|
|
May 25th Slow progress can be seen on the
Jackson Bridge.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
May 25th Piles of new lumber are ready to
be installed on the bridge.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Back to Top |
June 2007 |
|
|
June 26th |
|
|
|
June 26th The additional boards have arrived and
the workers are putting the bridge back together. The north cords and posts are
installed and the works are now working on the south end.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
June 26th There are still piles of new lumber
ready to be installed on the bridge.
|
|
|
|
|
|
|
|
June 26th Here are more of the boards that were
removed from the bridge.
|
|
|
|
|
|
|
|
|
|
|
|
June 26th Here are a series of pictures taken while
the workers were installing a section of the west arch.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Back to Top |
July 2007 |
|
|
July 15th |
|
|
|
July 14th The replacing of vertical posts
is ongoing, with only a few left to replace. The construction plan is
to install some of the roofing and siding before the bridge is moved back
over Sugar Creek. The moving crew was scheduled to arrive the week of
July 16th and start preparing for the move. The move is currently scheduled
for the middle of August.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
July 14th The post work is continuing on the
south end of the bridge.
|
|
|
|
|
|
|
|
|
|
|
|
July 14th There are still piles of boards
under tarps at the worksite.
|
|
|
|
|
|
|
|
July 14th Here are some close up shots of the
lower cords and posts that were replaced on the west side of the bridge.
|
|
|
|
|
|
|
|
|
|
|
|
July 14th Work has started on the south abutment.
|
|
|
|
|
|
|
Back to Top |