The Jackson Covered Bridge over Sugar Creek is being rehabilitated. Work
on the $1.4 million Federal Aid project is nearly complete. The project
included the removal of the roof and siding. The bridge frame was moved off of the abutments for the rehabilitation. The bridge was
removed from the abutments in February 2007. The bridge was put back on the abutments in August 2007. The purpose
of this website is to track the progress of the bridge rehabilitation.
August 2007 |
|
|
August 9th |
|
|
|
August 9th The
workers are trying to get as much done as possible
before the bridge is moved back over Sugar Creek.
The goal is to have the rafters and the bottom rows
of shingles installed while the bridge is on the
road. The workers also trying to install as
many siding supports as possible. Both of
these jobs will go slower if the work has to be
completed while the bridge is over the creek. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
August 9th
Architectural shingles are being installed.
The style was selected by the county commissioners.
They were also approved by the state agency. |
|
|
|
|
|
|
|
August 9th The
vertical cross supports have been installed in the
Jackson Covered Bridge. The vertical cross
supports are unique to the Jackson Covered Bridge.
|
|
|
|
|
|
|
|
August 9th The
temporary bridge has been constructed by the bridge
movers. The move is scheduled for August 15th
or 16th. |
|
|
|
|
|
|
|
August 9th New
abutments have been installed on the south approach
to the bridge. The north abutments cannot be
installed until after the bridge is moved. |
|
|
|
|
|
|
Back to Top |
August 15th |
|
|
|
August 15th The
Jackson Covered Bridge was scheduled to move on
August 15th or 16th. On August 15th the
decision was made to move the bridge on August 16th.
These pictures were taken in the morning before all
of the dollies had been installed. Later
in the day the final dollies were installed and the
bridge was moved closer to the creek.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Back to Top |
August 16th |
|
|
|
August 16th The
Jackson Covered Bridge was placed on dollies and
pulled onto the temporary bridge over Sugar Creek.
The actual move started around 9:15 am and completed
around 11:00 am. |
|
|
|
|
|
|
|
August 16th The
bridge builders were installing more siding nailers
before the bridge was moved. |
|
|
|
|
|
|
|
August 16th A
winch truck (red truck in background) was placed on
the south side of the Sugar Creek. Cables from
the winch were connected to the dollies supporting
the bridge. |
|
|
|
|
|
|
|
August 16th The
final supports were placed on the temporary bridge
before the move started. |
|
|
|
|
|
|
|
August 16th The
bridge was slowly winched into place. The next
two pictures were taken 3 minutes apart. |
|
|
|
|
|
|
|
|
|
|
|
August 16th The
first dolly goes onto the temporary bridge. |
|
|
|
|
|
|
|
August 16th
Workers closely watched the height of each dolly as
the bridge was moved. |
|
|
|
|
|
|
|
August 16th The
bridge is moved halfway onto the temporary bridge. |
|
|
|
|
|
|
|
|
|
|
|
August 16th The
rear set of dollies comes onto the temporary bridge. |
|
|
|
|
|
|
|
August 16th The
bridge was positioned at the south abutments. |
|
|
|
|
|
|
|
|
|
|
|
August 16th The
north end of the bridge is positioned where the
north abutment will be built. |
|
|
|
|
|
|
|
|
|
|
|
August 16th As
soon as the bridge was in place the workers begin
building supports so the dollies could be removed.
The bridge will rest on the temporary bridge until
the abutments are able to support the bridge. |
|
|
|
|
|
|
|
August 16th The
Jackson Covered Bridge is back in its home among the
trees. |
|
|
|
|
|
|
Back to Top |
|
|
August 22nd |
|
|
|
August 22nd The Jackson Covered
Bridge is sitting on the temporary bridge over Sugar Creek. The
workers are working on the south approach. |
|
|
|
|
|
|
|
|
|
|
|
August 22nd The north end of the
bridge is completely on pallets. The workers are building the
abutments by pouring cement and resetting the stones. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Back to Top |
September 2007 |
|
|
September 3rd |
|
|
|
September 3rd The work continues on
the north abutments. Forms have been set and concrete has been poured.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
September 3rd The arches are being completed
on the south abutment.
|
|
|
|
|
|
|
|
|
|
|
Back to Top |
September 13th |
|
|
|
September 13th Multiple crews are now working
on the Jackson Covered Bridge, trying to get it opened before the Parke
County Covered Bridge Festival. The roof crew has completed the new roof.
The siding crew has started siding the east side. Major work is still being
done on the north abutment. The first picture was taken from the south end
and shows a pile of prepainted siding waiting to be applied.
|
|
|
|
|
|
|
|
September 13th The siding has started to be
applied to the east side of the bridge.
|
|
|
|
|
|
|
|
|
|
|
|
September 13th Work still continues on the
north abutment. A hole has been dug, so footers can be poured.
|
|
|
|
|
|
|
|
September 13th The nailers have been applied
to the west side of the bridge. The crew will move to the west side as
soon as the east side is completed.
|
|
|
|
|
|
|
|
|
|
|
|
September 13th The cross supports on the
roof of the bridge are being installed. The flooring is also being bolted
into place.
|
|
|
|
|
|
|
|
|
|
|
Back to Top |
September 27th |
|
|
|
September 27th The Jackson Bridge is
starting to look like the old Jackson Bridge. Most of the siding has been
installed. The window openings have also been installed. The north
abutment still has significant work remaining. The dog house of the bridge
also needs to be constructed.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
September 27th The west side of the bridge
is nearly sided.
|
|
|
|
|
|
|
|
September 27th The east side of the bridge has
been sided except for the doghouse.
|
|
|
|
|
|
|
|
|
|
|
Back to Top |
October 2007 |
|
|
October 9th |
|
|
|
October 9th On October 9th the Jackson Covered
Bridge was opened to traffice. The bridge made the goal of being opened before
the start of the Parke County Covered Bridge Festival. Some small tasks still
remain (such as lettering the north end of the bridge). The bridge looks great
and was quiet as cars were driving across the bridge.
|
|
|
|
October 9th The lettering has been completed
on the south end of the bridge.
|
|
|
|
|
|
|
|
October 9th The following picture was taken
from the creek on the east side of the bridge.
|
|
|
|
|
|
|
|
October 9th The following pictures were taken
from the west side of the bridge.
|
|
|
|
|
|
|
|
|
|
|
|
October 9th The following pictures show the
north end of the bridge.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
October 9th The following pictures show some
of the architectural features of the bridge.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
October 10th |
|
|
|
October 10th The official ribbon cutting for the
Jackson Covered Bridge was held on October 10th. The ribbon was cut by County
Commissioner Greg Harbison, County Commissioner Jim Meece, and County Highway
Superintendent Randy Norman. Thanks to Ron Branson for the picture. Ron Branson is the
webmaster for the Indiana Covered Bridge Society website -
www.indianacrossings.org.
|
|
|
|
|
|
|
Back to Top |